Capital Plan Updates
NEW SOUTHWEST BRANCH / HEADQUARTERS
Estimated Cost = $23,025,000
PROject plan
Replace the Southwest Branch with a larger, modern Library constructed on land made available by Roy City
Project will be overseen by Prescott Muir Architects
Progress so far
- Site survey completed.
- Geotechnical report completed.
- Schematic design signed off.
- Design process completed.
- Project out to bid.
- Project completed.
OGDEN VALLEY BRANCH
Estimated Cost = $165,000
PROject plan
Add safe, street parking at the Ogden Valley Branch
Project will be overseen by Prescott Muir Architects
Progress so far
- Site survey completed.
- Geotechnical reports completed.
- Schematic design completed.
- Project has been awarded.
- Work accomplished.
- Quality review in progress.
- Project completed.
MAIN LIBRARY
Estimated Cost = $16,810,000
PROject plan
Renovate and upgrade the historic Main Library
Project will be overseen by EDA Architects, Inc.
Progress so far
- Asbestos abatement investigation completed.
- Water table mitigation investigation completed.
- Service space adjacency design underway.
- Schematic design signed off.
- Design development completed.
- Construction documents underway.
- Project awarded.
- Materials handling systems installed.
- Third floor construction completed.
- Books moved to second floor.
- Second floor construction completed.
- Books moved to first floor.
- Substantial completion.
- Technology infrastructure installed.
- Furniture installed.
- Soft opening.
- Grand opening.
NORTH BRANCH
Estimated Cost = $5,000,000
PROject plan
Modernize and double the space available to users of the North Branch
Project will be overseen by EDA Architects, Inc.
Progress so far
- Schematic design underway.
- Demolition completed.
- Materials handling systems reinstalled.
- Substantial completion.
- Technology infrastructure installed.
- Furniture installed.
- Books and materials moved to shelving.
- Grand opening.